Aging OKC Water Lines: 1,101 Main Breaks in Fiscal 2025, City Says

OKC water mains · AI narrator

OKLAHOMA CITY — Oklahoma City recorded 1,101 emergency water main breaks in fiscal year 2025, the city’s Utilities Department said, up from 621 the year before. City officials have said most of those breaks were in older sections of the roughly 4,300-mile system, mainly lines laid in the 1970s or before. On Wednesday morning, a 16-inch main broke near Northeast 36th Street and Kelley Avenue, flooding the intersection and closing it during repairs. The city has not said how old that main is or what caused the break.

Wednesday’s break at 36th and Kelley

FOX 25 reported that city crews got word of a major main break near N.E. 36th Street and Kelley Avenue around 5:30 a.m. Wednesday, Nov. 18, and found the intersection under water when they arrived. The station said several lanes were closed and advised drivers to expect delays or find another route. That story was posted at 7:14 a.m. CT.

KOCO, updated at 4:07 p.m. CT the same day, reported that Oklahoma City officials said maintenance crews were repairing a 16-inch water main, that the intersection had been shut down, and that motorists would have to use another route. City officials said, according to KOCO, that repairs could take six to eight hours after 9 a.m. Wednesday, and that about 25 to 30 customers had been affected. KOCO said its Sky 5 helicopter showed water covering the intersection as crews worked, and that some vehicles moved through the intersection before the roadway was closed.

As of the morning of Nov. 19, Facts First did not find a later update from KOCO, FOX 25, KFOR, News 9, or the city’s news site saying the intersection had reopened, that service had been fully restored, or that a boil-water advisory had been issued.

Break counts by fiscal year

The city said in a July 8, 2025, news release that its Utilities Department usually expects 600 to 800 emergency main breaks a year on about 4,300 miles of water line. The release listed these year-end counts of emergency breaks repaired:

Fiscal yearEmergency breaks repaired
FY 2023591
FY 2024621
FY 2025 (ended June 30, 2025)1,101

News 9 reported 1,022 water main breaks for fiscal 2025 in a June 9, 2025, story, three weeks before the fiscal year closed, up from 621 the year before. The story did not say through what date that count ran. It also reported that leaks rose to 3,246 from 2,903. The city’s July 8 year-end total of 1,101 covers the full year, so Facts First uses the city figure and notes the earlier News 9 count.

Facts First did not find an official city total for emergency breaks repaired in fiscal 2026, which ran from July 1, 2025, through June 30, 2026, or a count so far for fiscal 2027, which began July 1, 2026.

Why the city says pipes are failing sooner

The city’s July 8, 2025, release listed three factors behind the increase:

  • Pipe age. “Most of the breaks are occurring in older parts of the system, especially pipes installed in the 1970s or earlier.”
  • Material corrosion. Before the 1990s, the city said, it primarily used ductile iron pipe, which is susceptible to corrosion from highly corrosive soil in certain parts of the city. Starting in the early 1990s, the city said, it moved to corrosion-resistant pipe, including PVC, for lines of 16 inches or less.
  • Environmental stress. Officials said the clay soil common in Central Oklahoma expands when wet and contracts when dry, and that this movement, along with temperature swings, strains buried lines, older ones most of all.

Jasmine Morris, the utilities public information manager at the time, told News 9 in June 2025 that water mains “are designed to last close to 100 years” but that “we’ve seen some of them fail sooner than expected due to these conditions.” In a July 10, 2025, Journal Record story, Morris said the increase “isn’t simply aging pipe, but prematurely aging pipe caused by highly corrosive soil,” and that a high percentage of failures were in areas developed in the 1970s and 1980s, where ductile iron pipe “should last up to 100 years under normal conditions, but the corrosive soil has prematurely aged it.” The city release points to pipes from the 1970s or earlier; Morris’s Journal Record comments also included the 1980s.

What the city says about water pressure

In the same July 8, 2025, release, Utilities Director Chris Browning said the department’s data does not support the idea that high water pressure is causing the increase in breaks. “We’ve heard questions about whether high water pressure is causing the increase in line breaks, but our data doesn’t support that,” Browning said. “In fact, average discharge pressure at our Hefner Water Treatment Plant— which serves the area of OKC with the most breaks —has gone down over time and currently runs around 88 psi. That’s well within regulatory standards and much lower than pressure levels at our Draper plant, which averages between 118 and 128 psi.” That explanation is the city’s. Facts First has not independently reviewed the underlying pressure data.

What the city says it is spending

In its July 8, 2025, release, the city said the Utilities Department had raised yearly capital spending on water line replacement to $20 million starting in fiscal 2026 (July 1, 2025, to June 30, 2026), up from a historical level of about $10 million. The release said the department planned to raise that to $30 million in fiscal 2027, the fiscal year that began July 1, 2026. Facts First did not find a city document confirming the fiscal 2027 amount.

“Our crews work hard every day to restore service quickly and safely, but we also recognize the need for long-term solutions,” Browning said in the release. “That’s why we’re investing more than ever in replacing the necessary infrastructure. These improvements won’t happen overnight, but they are part of a sustained effort to strengthen our system, reduce future breaks and better serve the people of Central Oklahoma for decades to come.”

The city said it ranks replacement projects using break history, pipe age and material, and other risk measures, and that the added spending is part of the department’s financial plan and won’t directly raise customer bills.

Facts First could not find a current city figure for how many miles of water line are overdue for replacement, or a dollar estimate of a remaining replacement backlog. News 9 reported on July 10, 2026, that city officials said crews were backlogged on repairs during a heat wave, without giving a number.

A repeated break on one street, and a separate pipeline shutdown

KFOR reported that an eight-inch main broke early on a Wednesday in the 7000 block of North Stanley Avenue in the Lakeview neighborhood, leaving some homes without running water for hours. The KFOR story was listed Oct. 15, 2026, which puts that Wednesday on Oct. 14. The city told the station it was the street’s third break in two years, after breaks in the 6800 block in 2024 and the 6900 block in 2025.

Separately, Rural Water District No. 3, which is operated by the Citizen Potawatomi Nation, is preparing for a planned 14-day shutdown of Oklahoma City’s Atoka Pipeline beginning Nov. 30 to repair leaks. The district said the shutdown would cut the main supply to its southern service area, including communities south of Tecumseh, and that some customers may see reduced pressure or temporary interruptions, particularly in Maud and western Wanette. In a Nov. 18 update, the district said the Oklahoma Department of Environmental Quality had determined that a well in Asher could be connected to the system, and it listed locations where bottled water and non-potable water would be available. The district said no mandatory boil-water advisory was anticipated. The city’s 2023 drinking water report describes the Atoka pipeline as a 100-mile line that carries water from southeast Oklahoma into Stanley Draper Reservoir for treatment at the Draper plant. STV, on a project page for the second pipeline being built beside the original line, also describes a 100-mile pipeline. It is a separate system from the city distribution mains discussed above, and none of the break counts in this story include it.

Open questions

  • Had the intersection at Northeast 36th Street and Kelley Avenue reopened by the morning of Nov. 19, and was service fully restored for the customers the city said were affected?
  • How many emergency water main breaks did Oklahoma City repair in fiscal 2026, which ended June 30, 2026, and how many so far in fiscal 2027?
  • Does the city publish a current figure for miles of water line overdue for replacement, or for the cost of that remaining work?
The fence The 1,101 fiscal 2025 total comes from the city’s July 8, 2025, release. News 9 reported 1,022 breaks on June 9, 2025, before the fiscal year ended. Facts First has not independently tallied break records. KOCO said about 25 to 30 customers were “impacted” by Wednesday’s break; it did not say they had low or no water pressure. Facts First found no later official update on whether the repair was finished. The KFOR page on the North Stanley Avenue breaks returned an access error when retrieved for this story; the account above is from that report as excerpted in search results and dated Oct. 15, 2026, by Spot On Oklahoma.